| Location | Capacity kg/h |
Subject | Production Date |
| East Africa 2 | 3000 | Turnkey LABSA , SLES and acid absorption plant | Under Construction |
| Kangtai (Jinzhou) | 2000 | HABSA plant renovation, replace key equipment including sulfonator, ESP, main blower etc. | Under Construction |
| Shengtai (Taizhou) | 8000 | Turnkey LABSA SLES plant | Under Construction |
| Indonesia | 6000 | AOS unit | Under Construction |
| North Africa 3 | 6000+12000 | 6 tph LABSA SLES plant + 12 tph sulfuric acid + waste heat power generation with isolated grid self-use balance — a fully integrated turnkey project, equipped with a 144-tube new-generation sulfonator and unit 79 neutralization and dioxane stripping for dioxane removal | Under Construction |
| Salvador | 4000 | SLES Skid-mounted Dilution system, capacity 4tph to10tph adjustable | Under Construction |
| North Africa 2 | 2000+3000 | Italian existing plant revamp: Adding Unit 79 SLES Neutralization & dioxane stripping and Unit 89 multi-stage dioxane stripping, aiming for 1-2 ppm. | Under Construction |
| Sasol (China) | 1600 | SLES Neutralization feeding system renovation | Under Construction |
| Huimiao (Meishan) | 8000 | Process design and key equipment supply | Under Construction |
| Southern Africa | 3000 | Turkey LABSA SLES plant | Under Construction |
| East Africa 1 | 3000 | Turkey LABSA SLES plant | |
| Kenya 2 | 3000 | ESP replacement (replacing Italian cathod SS wires-type) | Under Construction |
| Chile | 2000 | ESP replacement (replacing Italian cathod SS wires-type) | Under Construction |
| Turkey | 8000 | Turnkey LABSA SLES plant, with 192-tube new generation reactor, neutralization and dioxane stripping, waste heat recovery, cold start-up, maglev main blower | Under Construction |
| Argentina | 3000 | SO3 cooler replacement | Under Construction |
| LG (South Korea) | 2000 | SO2 cooler replacement | Under Construction |
| India South 4 | 5000 | Turnkey LABSA SLES plant | Under Construction |
| Kenya 1 | 2000 | SO3 cooler replacement | Under Construction |
| Germany | 3800 | Unit 79 Neutralization and ultra-low dioxane SLES renovation, aiming for 1-2 ppm. | Under Construction |
| Russia 2 | 1600 | LABSA SLES turnkey plant with a single-tube pilot plant | Under Construction |
| Huimiao (Guangdong) | 5000+8000 | Process design and key sulfonation equipment | Under Construction |
| Wilmar (Tanzania) | 2000 | Unit 68 Waste Heat Recovery + SO3 cooler replacement | Under Construction |
| North Africa 1 | 2500 | Turnkey LABSA SLES plant, with Super Silicone Continuous Air Drying Technology (-70°C dew point, no two-tank switching fluctuations) | Under Construction |
| Jintung (Nanjing) | 5000 | 5tph Reactor and 8tph ESP | Under Construction |
| Solvay (India) | 3000 | AOS unit | Under Construction |
| South-East Asia | 8000 | Turnkey 8tph (with 192-tube reactor, the largest) LABSA and 10tph SLES SLS plant with Unit 69 Reaction heat recovery (for 15%+ electricity saving) and Unit 38 Waste Water Crystalization | Under Construction |
| India 5 | 40 | Turnkey single-tube pilot plant | 2026.5 |
| Lichen (Shanghai) | 7500*2 | Two sets of 178-tube new-seal sulfonators (three-center-tie-rod combined design), ensuring dual low levels of dioxane and free oil | 2026.4 |
| South Korea | 3800 | Unit 89 Dioxane Multi-stage stripping SLES renovation,dioxane content reduced to 1ppm | 2026.4 |
| Lichen (Shanghai) | 5000 | Unit 69 Reaction Heat Recovery conversion reaction heat recovery for steam production | 2025.9 |
| Lichen (Guangdong) | 7200 | ESP replacement (replacing Italian cathod SS wires-type) | 2025.9 |
| Richful (China) | 124.8 | 3-tube skid-mounted pilot plant | 2025.8 |
| Mexico | 5000 | SLES producing unit design ,key equipment supply, ESP replacement | 2025.6 |
| Honduras | 2000 | Turnkey LABSA plant | 2025.5 |
| Indonesia | 5000 | ESP replacement (replacing Italian cathod SS wires-type) | 2025.9 |
| Sasol (China) | 2000 | ESP and Sulfur furnance replacement (ESP replacement (replacing Italian type) | 2025.9 |
| Wilmar (Malaysia) | 3000 | Post degassing system | 2025.4 |
| Vietnam 4 | 7500 | Turnkey LABSA & SLES plant with 180-tube reactor, neutralization and dioxane stripping, waste heat recovery to realize hot water and steam self-sufficient, and cold start-up | 2025.2 |
| Bangladesh 2 | 2000 | Sulfonation Plant Phase 2: Adding SLES Unit 79 Neutralization & Dioxane Stripping with pH adjustment & auxiliary units. | 2024.9 |
| Weifang (China) | 3000 | Turnkey LABSA plant | 2025.1 |
| Sinolight (Shaoxing) | 5000 | 120-tube reacter set replacement | 2024.12 |
| Indonisia | 5000 | Old control system upgrade and 6tph ESP replacement | 2024.9 |
| Farabi (Saudi Arabia) | 41.6 | 1-tube skid-mounted pilot plant | 2024.9 |
| Russia | 3800 | Exhuast gas treatment renovation and neutralization reactor replacement | 2024.8 |
| Lichen (China) | 7000 | Revamp non-backmixing static mixed aging system, active matter ≥ 97.5% | 2024.8 |
| Indonesia | 5000 | Multiple ESPs replacement (replacing Italian cathod SS wires-type) | 2024.7 |
| West Asia | 3000 | Reactor replacement | 2024.6 |
| Chile | 2000 | Reaction tube replacement | 2024.6 |
| Richful (China) | 5000 | Turkney HABSA plant, with Unit 68 waste heat recovery system | 2024.5 |
| Solvay (China) | 1000 | Exhuast gas treatment renovation | 2024.4 |
| Argentina | 4000 | 2tph SO2 cooler (310S) + 4tph ESP replacement | 2024.1 |
| Ethiopia | 3000 | 3000m3 palm oil storage tank farm | 2024.1 |
| Egypt | 3000 | Scrubber, heat exchanger and ESP replacement | 2024.1 |
| Solvay (India) | 3000 | ESP replacement | 2023.12 |
| India 1 | 4000 | Reactor replacement | 2023.11 |
| Lizhi (Guangdong) | 3800 | Ultra-low dioxane SLES renovation for meeting P&G's future requirement | 2023.11 |
| Sinolight (Shaoxing) | 5000 | Revamping from 3.8tph to 5tph SLES plant, including reactor and other key equipment | 2023.9 |
| Bangladesh 2 | 2000 | Turnkey LABSA plant with Waste Heat Recovery | 2023.7 |
| Lichen (Changsha) | 208 | Turnkey 5-tube pilot plant for producing IOS and other small batch products | 2023.6 |
| China National Institute of Chemical Industry (CNIC) | 2000 | C15 alpha-olefin sulfonation sulfonate research project | 2023.6 |
| Egypt | 3000 | ESP replacement | 2023.4 |
| Petrochina (Huayang) | 1600 | Unit 68 waste heat recovery system | 2023.3 |
| Ethiopia | 3800 | Turnkey LABSA and sulphuric acid integrated plant (1.2tph 98% sulphuric acid capacity) , with Unit 38 Waste Water Evaporation and Cystalization | 2023.2 |
| India 3 | 7000 | ESP replacement | 2023.1 |
| Sasol (China) | 1600 | Acid Absorption Unit | 2023.1 |
| Jintung (Nanjing) | 3800 | Unit 68 Waste Heat Recovery | 2022.11 |
| Shengtai (Taizhou) | 6000+5000 | Turnkey LABSA SLES AOS plant | 2022.9 |
| Pakistan 3 | 3000 | LABSA SLES Turnkey plant with Unit 69 Reaction Heat Recovery | 2022.8 |
| Pakistan 1 | 6000 | LABSA turnkey plant (second phase) , 144-tube new-gen reactor, SLES dilution for the first plant | 2022.6 |
| Jintung (Sichuan) | 3800*2 | Unit 68 Waste Heat Recovery | 2022.4 |
| Turkey | 6000 | Turnkey LABSA SLES SLS plant with European Union PED Standard | 2022.2 |
| Huimiao (Meishan) | 7500 | 7.5tph LABSA 10tph SLES SLS 15tph AOS plant with 180-tube reactor and waste heat recovery | 2022.2 |
| Lichen (Changsha) | 4000+5000 | Unit 69 Reaction Heat Recovery | 2022.2 |
| Yifeng (China ) | 120 | 3-tube reactor pilot plant | 2022.2 |
| Sinopec (Chengdu) | 2000 | ESP replacement | 2022.1 |
| Tianhong (Anyang) | 2000 | Reactor and aging vessel | 2022.1 |
| Vietnam 1 | 3000 | Adding Unit 68 Waste Heat Recovery | 2022.1 |
| Jintung (Anhui) | 5000+1000 | Unit 79 Neutralization revamping | 2021.12 |
| Jintung (Sichuan) | 3800 | Unit 79 SLES neutralization and 68 revamping | 2021.12 |
| Vietnam 1 | 3800 | Unit 68 waste heat recovery and SO3 cooler | 2021.8 |
| ZZY (Meishan) | 3800*2 | Weixian new-gen reactor | 2021.7 |
| India 4 | 5000 | Turnkey LABSA SLES SLS Unit 69 Reaction Heat Recovery | 2021.4 |
| Bangladesh 1 | 1000 | Turnkey LABSA SLES plant | 2022.2 |
| West Asia 2 | 1200 | Turnkey LABSA SLES plant | 2022.2 |
| Pakistan 2 | 6000 | Turnkey LABSA SLES plant with Unit 68 and SLES Dilution | 2021.2 |
| Indonesia | 6000 | Turnkey LABSA SLES Unit 68 plant | 2021.11 |
| Yeman | 2000 | Reactor replacing Italian one | 2021.5 |
| ZZY (Henan) | 5000*4 | 4 New-gen Reactors with Exhaust circulation process, sulfur buring and SO3 convertion | 2021.1 |
| Sinolight (Shaoxing) | 3800 | Old plant Exhaust Treatment and organic material recovery revamping, reducing carry over in exhaust by 50%+ | 2021.11 |
| Sinolight (Shaoxing) | 6000 | Turnkey LABSA SLES plant with Unit 68 waste heat recovery system,Unit 38 waste water crystallization and Unit 08 SO3 absorption for sulphuric acid production, world's first 4-layer layout design | 2021.6 |
| India 1 | 5000 | Turnkey LABSA, SLES and SLS plant with Unit 69 | 2021.4 |
| Jintai (China) | 2000 | Static-mixing level-controllable aging and stabilization | 2021.1 |
| Shandongweifang (China) | 5000 | New-gen reactor replacing old one | 2020.11 |
| Shandong Jining (China) | 3800 | LABSA SLES AOS turnkey plant design | 2020.1 |
| India 1 | 4000 | Turnkey LABSA SLES AOS SLS plant with Unit 69 | 2020.9 |
| Tianzhi (China) | 3800 | The second Unit 79 Neutralization replacing Double-step Neutralization | 2020.9 |
| Tianhong (Anyang) | 800 | 19-tube reactor replacing the old one | 2020.8 |
| Huimiao (Xinxiang) | 1000 | SLS Film scraping, drying, tablet pressing and needle extrusion plant | 2020.8 |
| Anhuianqing (China) | 3800 | Weixian reactor replacing Italian one for LABSA SLES AOS production | 2020.7 |
| Lichen (Shanghai) | 10000 | The largest 10tph ESP | 2020.6 |
| Lichen (Guangdong) | 6000*2 | Two reactors replacing Italian ones and Unit 38 | 2020.4 |
| ZZY (Jiaxing) | 3800 | Adopting Weixian reactor with liquid SO3 evaporation and exhaust circulation process | 2020.4 |
| Shandonglongkou (China) | 2000 | Turnkey LABSA plant | 2020.3 |
| Lichen (Shanghai) | 6000+5000 | New 6tph plant and old 5tph Italian plant revamping including replacing reactor | 2020.3 |
| Lichen (Changsha) | 5000 | 5tph New waste heat systme, 5tph aging vessel*2, 3.8tph ESP*2 | 2020.3 |
| India 3 | 6000 | Turnkey LABSA plant with Unit 79 and 68 | 2019.9 |
| Vietnam 3 | 3000 | Turnkey LABSA with Unit 68 | 2019.9 |
| Sasol (China) | 1600 | Weixian reactor replacing Italian one, for sulfation of various fatty alcohol ethers | 2019.9 |
| Vietnam 2 | 1600 | Turnkey SLES plant Unit 79 | 2019.8 |
| Huimiao (Xinxiang) | 1000 | SLS film Scraping drying plant | 2019.6 |
| Sudan | 2500 | Turnkey LABSA SLES Unit 68 | 2019.6 |
| Zhisheng (Huizhou) | 3800 | Unit 79 Neutralization replacing Vacuum Neutralization | 2019.3 |
| India 2 | 2000 | Weixian reactor replacing Italian one for LABSA SLES and AOS producetion | 2019.2 |
| Jintung (Sichuan) | 3800 | Unit 79 SLES Neutralization replacing Double-step Neutralization | 2019.2 |
| Vietnam 1 | 3000 | Neutralization reactor and waste heat recovery | 2019.12 |
| Pakistan 1 | 3000 | Turnkey LABSA SLES Unit 68 | 2019.1 |
| Huimiao (Xinxiang) | 3800+6000 | Turnkey LABSA SLES AOS SLS plant with Unit 38 Unit 69 | 2019.1 |
| Ethiopia 1 | 1600 | Turnkey SLES Unit 79 | 2018.9 |
| South Korea | 3800 | Revamping old Italian SLES neutralization and adding pump neutralization | 2018.7 |
| Iiby (Guangzhou) | 1600 | Replacing old reactor for AOS production | 2018.6 |
| Jintung (Anhui) | 3800 | SLES Unit 79 and Unit 68 waste heat recovery | 2018.5 |
| Shijiazhuang (China) | 600 | MES turnkey plant with 14-tube reactor | 2018.4 |
| South Korea 1 | 6000 | Turnkey LABSA SLES plant with Unit 68 | 2018.2 |
| Shengtai (Lianshui) | 2000*2 | Two LABSA SLES AOS plants | 2017.8 |
| South Korea 1 | 2500 | Weixian ESP replacing American one | 2017.2 |
| Hongtai (Xinxiang) | 3800 | Turnkey LABSA SLES with Unit 68 | 2017.11 |
| Shengtai (Xinjiang) | 2000 | Turnkey LABSA SLES plant with Unit 38 Waste Water Evapration and Cystalization | 2017.11 |
| Libo (Shangdong) | 3800 | SO2 cooler and SO3 cooler replacement | 2017.6 |
| Yishui (Dongxin) | 2000 | LABSA Turnkey plant | 2017.1 |
| Tianhong (Anyang) | 800+1300 | Two turnkey plant with a 3-stage Waste Heat Recovery for hot water genaration | 2017.1 |
| Ethiopia 1 | 1600 | Turnkey LABSA SLES plant with Unit 68 | 2016.7 |
| Xinya (Anyang) | 3800 | Weixian Unit 79 Neutralization replacing Vacuum Neutralization | 2016.5 |
| Tianzhi (Tianjin) | 3800 | Weixian Unit 79 Neutralization replacing Double-step Neutralization | 2016.4 |
| India 1 | 2000 | Weixian 48-tube reactor replacing Italian | 2016.3 |
| Hongtai (Xinxiang) | 2000 | Weixian new reactor replacing old one and adding AOS | 2016.11 |
| Vietnam 1 | 3000 | Reactor and Unit 79 | 2015.5 |
| Liby (Kunming) | 3800 | Critical equipment | 2015.7 |
| Shandonglongkou (China) | 2000 | Turnkey LABSA SLES Unit 68 | 2014.4 |
| West Asia 1 | 2500 | Weixian reactor replacing Italian one | 2014.7 |
| Dongxin (Jinan) | 2000 | AOS plant | 2014.10 |
| Xinya (Anyang) | 40 | Pilot plant | 2013.2 |
| Hongtai (Xinxiang) | 2000 | Turnkey LABSA SLES AOS plant with Unit 68 | 2013.9 |
| Shengtai (Lianshui) | 3800 | Turnkey SLES plant Unit 79 and Unit 68 | 2013.8 |
| P&G (Beijing) | 2000 | American plant renovation with new reactor,aging and hydrolysis, SO3 cooling and air drying units | 2013.5 |
| Sasol (China) | 1600 | Unit 79 Neutralization replacing Double-step Neutralization, 1-4 dioxane content 3ppm | 2013.7 |
| Jinzhou (Hebei) | 2000 | Turnkey LABSA.SLES | 2012.2 |
| Vietnam 1 | 3000 | Critical equipment and Unit 79 | 2012.2 |
| Jintung (Sichuan) | 3800*2 | One Unit 68 Waste Heat for two plants | 2012.1 |
| Syria | 1000 | LABSA and SLES turnkey plant | 2012.2 |
| Dongxin (Shandong) | 1100 | Turnkey LABSA plant | 2012.6 |
| ZZY (Shaoguan) | 3800 | Turnkey LABSA SLES plant | 2012.6 |
| Jingdi (Shanghai) | 6000 | ESP Disc-and-tube type | 2012.5 |
| Tongye (Shijiazhuang) | 1200 | LABSA turnkey plant | 2012.3 |
| Jintung (Nanjing) | 3800 | Waste heat recovery | 2012.2 |
| Jintung (Anhui) | 120 | 3-tube reactor pilot plant | 2011.12 |
| Fushun (China) | 1600 | Turnkey LABSA | 2011.2 |
| Rongchao (Xinji) | 400 | Oil sulphonation | 2011.8 |
| Tianhong (Anyang) | 1200 | New generation reactor and ESP replacement | 2011.1 |
| Note: shown above are just partial projects of Weixian |
|||