Replacing a 6-ton ESP: On-Site Commissioning by Our Experts
Oct 16, 2025We are guiding the replacement of a original Italian ESP with a WEIXIAN 6-ton unit. Our engineers are on-site to supervise the installation and prepare for commissioning.
Key activities included:
✅ Protective Air Flow Checked: Verified the protective air delivery pipelines to ensure uniform hot air protection for porcelain insulators.
✅ Critical Baffles Installed: Supervised the installation of PTFE baffles between the cathode frame and insulator compartments.
✅ Precision Alignment: Corrected the concentricity of the cathode rods for optimal performance.
✅ Blower Pressure Tested: Confirmed the new protective air blower is operating at the required pressure.
✅ Electrical Safety Verified: Thoroughly inspected all grounding and high-voltage connections.
This careful precommissioning will prepare the system for reliable, long-term operation.
![]() |
![]() |
![]() ![]() |
![]() |